题目详情
题目详情:
发布时间:2023-10-20 20:50:45

[单项选择]

Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.


A. analyze
B. track
C. level
D. extend

更多"Developing the project schedule is "的相关试题:

[单项选择]

The inputs of developing project management plan do not include()


A. project charter
B. stakeholder management strategy
C. project scope statement
D. outputs from planning processes
[单项选择]

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.


A. activity duration estimating, schedule developing, activity resource estimating
B. activity resource estimating, activity duration estimating, schedule development
C. schedule developing, activity resource estimating, activity duration estimating
D. activity resource estimating, schedule developing, activity duration estimating
[单项选择]

Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().


A. crashing the schedule
B. performing resource leveling
C. conducting reverse resource allocation scheduling
D. utilizing the critical chain resources
[单项选择]

(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity.

空白(1)处填()
A. PDM
B. CPM
C. PERT
D. AOA
[单项选择]

Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.

空白(1)处填()
A. accuracy
B. approximation
C. specification
D. summary
[单项选择]What promotes Third Part Logistics developing its business? ()
A. Outsourcing 
B. Transporting  
C. Warehousing  
D. Distributing
[单项选择]

The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.


A. estimating
B. defining
C. planning
D. sequencing
[单项选择]在Project2003中删除任务,需要打开Project文档,并切换到在()视图。
A. 绘图
B. 甘特图
C. 列表
D. 工具
[单项选择]Crude oil carriers often use ()
A. Big ships
B. Huge ships
C. Large container ships
D. Supertankers
[单项选择]

Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.


A. Benefitcontribution
B. Expertjudgment
C. Scoringmodels
D. Flowcharting
[单项选择]

Project work packages are typically decomposed into smaller components called activities to provide a basis for()scheduling, executing, and monitoring and controllingthe proj ect work.


A. reviewing
B. estimating
C. auditing
D. expecting
[单项选择]

Project Quality Management must address the management of the project and the()ofthe project. While Project Quality Management applies to all projects,regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.


A. performance
B. process
C. product
D. object
[单项选择]

Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.


A. Project
B. project management team
C. performingorganization
D. customer

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码