[单项选择]An example of risk mitigation is______.
A. using new technology in the development of a product
B. purchasing insurance
C. eliminating the cause of risk
D. accepting a lower profit if costs overrun

更多"An example of risk mitigation is___"的相关试题:

[单项选择]The 1983 report"A Nation At Risk"cited as example of the decline of educational standards()
A. high rates of adult illiteracy
B. declining SAT scores
C. low scores of American students in key subjects as compared with scores of students of other countries
D. All of the above
[单项选择]Which of the following mitigation techniques would an administrator apply to a device in order torestrict remote access?()
A. Disable TELNET
B. Disable IGMP snooping
C. Enable TELNET but not SSL
D. Disable ICMP/ping on device
[单项选择]Which of the following security mitigation techniques is the MOST effective against zero-day attacks?()
A. Update antivirus definitions
B. MAC filtering
C. Effective security policies
D. User awareness training
[单项选择]Market risk refers to the risk of ______.
A. default
B. financial prices fluctuation
C. fraud
D. deferred payment
[单项选择]Risk management helps in maximizing the probability and consequences of positive events and minimizing the probability and consequences of adverse events to project objectives.Risk response planning helps in this context because it______.
A. helps in deciding how to approach and plan the risk management activities
B. develops procedures and techniques to enhance opportunities and reduce threats to project objectives
C. determines which risks might affect the project and documents their characteristics
D. monitors residual risks,identifies new risks and executes risk reduction plans
[单项选择]An appropriate sequence for risk management activities is______.
A. identify risks,perform qualitative risk analysis,perform quantitative risk analysis,plan risk responses
B. identify risks,risk assessment。and risk planning
C. identify risks,risk mitigation,and risk management
D. identify risks,risk elimination,and risk mitigation
[单项选择]Risk management allows the project manager and the project team net to ( ).
A. eliminate most risks during the planning phase of the project
B. identify project risks
C. identify impacts of various risks
D. plan suitable responses
[单项选择]Broadsides could be published with little risk to colonial printers because they
A. ( required a small financial investment and sold quickly
B. ( were in great demand in European markets
C. ( were more popular with colonists than chapbooks and pamphlets
D. ( generally dealt with topics of long-term interest to many colonists
[单项选择]If the phenomenon "extinction risk increased significantly with decreasing heterozygosity" (lines 9-10) agrees with the proposed effect on extinction, the passage assumes
A. (A) heterozygosity is an indicator of increasing inbreeding depression in assimilated metapopulations
B. (B) heterozygosity is unrelated to the degree of inbreeding depression in assimilated metapopulations
C. (C) heterozygosity is an indicator of decreasing inbreeding depression in isolated metapopulations
D. (D) heterozygosity is an indicator of increasing inbreeding depression in isolated metapopulations
E. (E) heterozygosity is an indicator of decreasing inbreeding depression in assimilated metapopulations
[单项选择]Risk factors related to opportunities for fraud invlude:()
A. The nature of the industry or operations.
B. Threats to the firms' financial stability or profitability.
C. Complex or unstable organizational structure.
[单项选择]The most crucial time for project risk assessment is______.
A. when a problem surfaces
B. during the planning phase
C. during the close-out phase
D. after the project schedule has been published
[单项选择]The tools and techniques of quantitative risk analysis are______.
A. contracting,contingency planning,alternative strategies,and insurance
B. interviewing,historical results,workarounds,and additional response development
C. checklists,damage control reports,standard allowances, and inspection
D. data gathering and representation techniques,and quantitative risk analysis and modeling techniques
[单项选择]Outputs from risk response planning include all of the following EXCEPT______.
A. risk register updates
B. corrective actions
C. risk-related contractual agreements
D. project management plan updates
[单项选择]The employees tried to avoid every risk that might ______ her displeasure during the first month after she was divorced by her husband.
A. indebt
B. indicate
C. incur
D. incline
[单项选择]According to the passage, the greatest risk posed by the feminist theories, like the Female Aesthetic, which posit the existence of an "essential" or non-constructed gender is in
[单项选择]In risk response planning,an acceptance strategy indicates that the project team has decided______.
A. to agree with the project manager
B. to eliminate a specific threat
C. not to change the project management plan to deal with a risk,or is unable to identify any other suitable response strategy
D. to purchase insurance
[单项选择]All of the following are inputs to risk identification EXCEPT______.
A. risk management plan
B. project management plan
C. workaround plan
D. project scope statement
[单项选择]All the following are purposes of project risk management EXCEPT______.
A. identifying factors that are likely to affect the project scopquality,time and cost
B. developing response strategies for all identified risks
C. providing a baseline for project factors that cannot be controlled
D. mitigating impacts by influencing project factors that can be controlled
[单项选择]The main risk faced by an individual who enters into a forward contract to buy the S&P 500 Index is that

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码