[单项选择]The project team has just completed the initial project schedule and budget.The NEXT thing to do is ().
A. begin risk identification
B. begin iterations
C. determine communications requirements
D. create a bar(Gantchart

更多"The project team has just completed"的相关试题:

[单项选择]The PM and the project team have completed decomposition and have verified scope, when the marking department makes a minor change to the product functionality to improve its appeal to the end customer. The PM and the project team ______ .
A. refuses to accept the change since the scope has been verified
B. modifies the WBS and the decomposition
C. accepts the change and incorporates it into the WBS, modifying the budget and the schedule and assigning accountability to the marking team
D. proceeds per the change process
[单项选择]The current general slackness of the market has prevented us from ______ new orders with you.
A. placing
B. putting
C. arranging
D. providing
[填空题]After she completed the project, she' ll have______(没什么要担心的). (worry)
[单项选择]All technical work is completed on the project.Which of the following remains to be done ?()
A. Verify scop
B. Risk response pla
C. Staffing management pla
D. Lessons learne
[单项选择] The sales team has just sold the first pSeries solution to a Windows NT customer.   The team has identified concerns with a non-existent backup strategy and some workable environmental issues.   In addition to these concerns,what other major concern should be considered?()
A. Customer skill level
B. Hardware availability
C. Lack of executive sponsorship
D. Hardware and software compatibility
[单项选择]The project is not completed until ().
A. the project scope is completed,administrative closure is completed and payment is received
B. formal acceptance is received,and any other requirements for project closure as stated in the contract are met
C. the customer is satisfied and final payment is received
D. lessons learned are completed
[单项选择]An international team of astronomers has discovered 11 new planets outside the solar system, raising fresh ______ about the possibility of life in outer space.
A. exploring
B. debate
C. wondering
D. pondering
[单项选择]A project management team has subcontracted work to a service company.Which of the following tools is the best choice to assure that this company will be able to meet the quality requirements of the project ?()
A. Quality audi
B. Deliverable inspectio
C. Fixed price contrac
D. Service level agreemen
[单项选择]The project team has added some additional functionality which was not required as part of the project. However the customer is satisfied with the project. From a quality perspective, ______ .
A. this is high quality because it exceeded customer expectations
B. this is not acceptable quality because gold plating was done which is not advisable
C. this will mean repeat business from the same customer
D. none of the above
[单项选择]What he has just said has little to do with the question ______ discussion.
A. on
B. under
C. in
D. at
[单项选择]Living in the central Australian desert has its problems, ______ obtaining water is not the least.
A. for which
B. to which
C. of which
D. in which

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码