[单项选择]The project will be a ______ plan to build more than 100 town homes, restaurants and retail space around the city.
A. 34 million dollar
B. 34 millions dollar
C. 34 million dollars
D. 34 millions dollars

更多"The project will be a ______ plan t"的相关试题:

[单项选择]The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a ( ).
A. Project Scope Statement
B. Project Management Plan
C. Forecasts
D. Project Charter
[单项选择]The inputs of developing project management plan do not include()
A. project charter
B. stakeholder management strategy
C. project scope statement
D. outputs from planning processes
[单项选择]A project management plan should be realistic in order to be used to manage the project.Which of the following is the BEST method to achieve a realistic project management plan ?()
A. Sponsor creates the project management plan based on input from the project manage
B. Functional manager creates the project management plan based on input from the project manage
C. Project manager Creates the project management plan based on input from senior managemen
D. Project manager creates the project management plan based on input from the tea
[单项选择]The rate of contribution to the pension plan is the same for all employees, _______ age.
A. with the exception of
B. regardless of
C. by virtue of
D. in the light of
[单项选择]It is difficult to get young people to plan for their old age, which seems very distant to them.
A. impossible
B. faraway
C. observable
D. fearful
[单项选择]As a project manager,project plan development is an important element of managing projects.Which phase of the project management life-cycle does project plan development belong to ?()
A. Initiation proces
B. Planning proces
C. Execution proces
D. Controlling proces
[单项选择]In your software development project you have planned for system testing from March 1st and the duration is 10 days.Two days before the completion of the system test,you can start the user acceptance test.The 2 days in this case is an example of ().
A. lead
B. lag
C. delay
D. float
[单项选择]You prepared an integrated project plan and a project schedule.You submitted it to the steering committee,and it was approved.Key stakeholders accepted the plan.It is time to distribute it.Both the project plan and schedule should be distributed to______.
A. all stakeholders in the performing organization
B. all project stakeholders
C. project team members and the project sponsor
D. people noted in the communications management plan
[单项选择]The reason tourism benefits a country even more than traditional industries is that it __________.
A. requires much less capital
B. has more of a cultural benefit
C. has more potential to lead to other industries
D. uses less resources which harm the environment
[单项选择]Before 1500 North America was inhabited by more than 300 cultural groups, each with different customs, social structures, world views, and languages. Such diversity ______ the existence of a single Native American culture.
A. complements
B. implies
C. reiterates
D. argues against

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码