更多"Your project is behind schedule due"的相关试题:
[单项选择]Due to cuts in funding, your project has been terminated. The scope verification process ______
A. Should be delayed until the project is completed.
B. Should determine the correctness of the work results.
C. Should establish and document the level and extent of completion.
D. Will form the basis of the project audit.
[单项选择]Mother: Jimmy, what are you hiding behind your back Let me see.
Jimmy: It's kitty. Please let me keep it. It's a good kitty and will not bring you any trouble.
Mother: ______ I told you. No pets. It'll make a mess of this house.
A. No way
B. Not at all
C. By the way
D. On the contrary
[单项选择]The previous project manager for your project managed it without much project organization. There is a lack of management control and no clearly defined project deliverables. Which of the following would be the BEST choice for getting your project better organized
A. Adopt a life cycle approach to the project.
B. Develop lessons learned for each phase.
C. Develop specific work plans for each work package.
D. Develop a description of the product of the project.
[单项选择]While working on an external project your customer asks you to perform some additional tasks that are not included in the formal contract.You should ().
A. honor the customer's request as sign of cooperation to ensure future business
B. refuse the request and report the customer to your sponsor
C. acknowledge the request and advise the customer to submit a formal change request
D. convene a meeting of the project team and rewrite the scope statement
[单项选择]Your schedule analysis has shown that your project has a high likelihood of experiencing a schedule overrun. You know this because the cumulative EV is much ().
A. higher than the cumulative AC
B. higher than the cumulative PV
C. lower than the cumulative PV
D. lower than the cumulative CPI
[单项选择]What is the premise behind a project of the Massachusetts Institute of Technology
A. Electronic ink.
B. Electronic book.
C. Laptop.
D. LCD screen.
[单项选择]Your project involves manufacturing high precision engine subassemblies for the shipping industry. You have to perform several activities such as measuring, examining. and verifying to determine whether work and deliverables meet requirements and product acceptance criteria. You would have to do several reviews, product reviews, audits and walkthroughs. These activities are carried out in which process ?()
A. Verify scope
B. Quality inspection
C. Scope planning
D. None of the above
[单项选择]Your project team identified six related projects with major dependencies on your deliverables. Some of these projects have a very similar scope and may overlap with your deliverables. In Light of this, which of the following should you be MOST concerned about ?()
A. Scope change control
B. Scope verification
C. Risk response planning
D. Communications planning
[单项选择]Your project has a number of different work results. You are collecting information about these work results such as what costs have been incurred or committed and which deliverables have been completed and which remain outstanding. You will use this information in which of the following processes
A. Direct and manage project execution.
B. Perform integrated change control.
C. Reprot performance.
D. Verify scope.
[单项选择]Your failure in the final examination is due to the fact that you didn't _______ enough importance to your English.
A. attend
B. attack
C. attach
D. obtain
[单项选择]In your project, you have started doing human resource planning and are studying the interpersonal relationships among the candidates who are being considered for the project team. Some factors you consider include: What type of formal and informal reporting relationships exist amongst the candidates for the project team What are the candidate's job descriptions What are the supervisor-subordinate relationships What cultural or language differences will affect working relationship between team members What levels of trust and respect currently exist All this information will be available as part of ().
A. enterprise environmental factors
B. organization hierarchy
C. informal reporting relationships
D. all of the above
[单项选择]As a project manager of IT, if your supplier asked you to provide a product description, which of the fowling is ().
A. scope statement
B. statement of work
C. project charter
D. contract