[单项选择]The project consists of 15 separate projects. The PMO will have a project management information system. This system will be an on-line repository of all program data. You will collect description of all work components for each of the 15 projects. This information will form an integral part of the (). A. chart of account B. WBS dictionary C. WBS structure template D. earned value management reports