[单项选择]Both under-communication and over-communication can cause problems on a project.You want to ensure that the information you collect showing project progress and status is meaningful to stakeholders.To determine specific metrics,you will conduct a stakeholder analysis,and then determine the level of detail stakeholders require.This is available through the______. A. performance measurement baseline B. project management methodology C. project strategy and approach D. communications management plan