[单选题]The Develop Project Management Plan Process includes the actions necessary to define, prepare,integrate, and coordinate all constituent plans into a ( )
A.Project Scope Statement
B.Project Management Plan
C.Forecasts
D.Project Charter
[单选题]Establishing a project ( ) involves listen milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element
A.cost management plan
B.risk management plan
C.soope management plan
D.management schedule
[单选题]Establishing a project(74)involves listen mile stones,activities,and deliverables with intend start and finish dates of which the scheduling of employees may be an element.
A.cost management plan
B.risk management
C.scope management plan
D.management schedule
[单选题]Risk management allows the project manager and the project team not to()
A.eliminate most risks during the planning phase of the project
B.identify project risks
C.identify impacts of various risks
D.plan suitable responses
[单选题]In project management and systems engineering,( )is a deliverable-oriented breakdown of a project into smaller components.It is a key project deliverable that organizes the team's work into manageable sections.
A.RBS
B.PBS
C.GBS
D.WBS
[单选题]Project Integration Management includes the processes and activities to identify,define,combine,unify,and coordinate the various processes and project management activities within the Project Management Process Groups.( )process does not belong to Project Integration Management.
A.Developing project charter
B.Developing project management plan
C.Analyzing project risks
D.Monitoring and controlling project
[单选题]( )is a project management technique for measuring projectPerformance progress.It has the ability to combine measurements of the project management triangle: scope,time and costs.
A.Critica1 path method(CPM)
B.Earned value management(CEV)
C.Net present value method(NPVM)
D.Expert judgment method(EJM)
[单选题]The inputs of developing project management plan do not include()
A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes
[单选题]In project time management,activity definition is the process of identifying and documenting the specification to be performed to produce the project deliverables.( )are not output of activity definition.
A.Activity list
B.Work Break down Structures
C.Activity Attributes
D.Mile stone Lists
[单选题]The Project Management Triangle is a model of the constraints of projectmanagement.These constraints have been listed scope(or quality),(73),and cost.
A.resource
B.time
C.plan
D.tool
[单选题]The project management plan defines how the project is executed,monitored and controlled,and closed.It is progressively elaborated by updates,and controlled and approved through the perform integrated( )process.
A.Cost control
B.Schedule control
C.Change control
D.Risk control
[单选题]Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order.
A.activity duration estimating, schedule developing, activity resource estimating
B.activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating