[单选题]As the degree of sensitivity of a project to a single variable rises, the:
A. less important the variable is to the final outcome of the project.
B. less volatile the project's net present value is to that variable.
C. greater is the importance of accurately predicting the value of that variable.
D. greater is the sensitivity of the project to the other variable inputs.
E. less volatile is the project's outcome.
Difficulty: 1 Easy
Topic: Sensitivity analysis
Learning Objective: 11-01 Perform and interpret a sensitivity analysis for a proposed investment.

更多"[单选题]As the degree of sensitivity o"的相关试题:

[单选题]Combining scenario analysis with sensitivity analysis can yield a crude form of ________ analysis.
A. forecasting
B. combined
C. complex
D. simulation
E. break-even
Difficulty: 1 Easy
Topic: Simulation analysis
Learning Objective: 11-02 Perform and interpret a scenario analysis for a proposed investment.
[单选题]Sensitivity analysis determines the:
A. range of possible outcomes given that most variables are reliable only within a stated range.
B. degree to which the net present value reacts to changes in a single variable.
C. net present value range that can be realized from a proposed project.
D. degree to which a project relies on its initial costs.
E. ideal ratio of variable costs to fixed costs for profit maximization.
Difficulty: 1 Easy
Topic: Sensitivity analysis
Learning Objective: 11-01 Perform and interpret a sensitivity analysis for a proposed investment.
[单选题]The price sensitivity of a bond increases in response to a change in the market rate of interest as the:
A. coupon rate increases.
B. time to maturity decreases.
C. coupon rate decreases and the time to maturity increases.
D. time to maturity and coupon rate both decrease.
E. coupon rate and time to maturity both increase.
Difficulty: 1 Easy
Topic: Interest rate risk
Learning Objective: 07-02 Explain bond values and yields and why they fluctuate.
[单选题]A project's cash flow is equal to the project's operating cash flow:
A. plus the project's depreciation expense minus both the project's taxes and capital spending.
B. minus both the project's change in net working capital and capital spending.
C. minus the project's change in net working capital plus all of the depreciation expenses.
D. plus the project's depreciation expenses minus the project's taxes.
E. minus the project's taxes.
Difficulty: 1 Easy
Topic: Cash flows
Learning Objective: 10-01 Determine the relevant cash flows for a proposed project.
[单选题]As the degree of financial leverage increases, the:
A. probability a firm will encounter financial distress increases.
B. amount of a firm's total debt decreases.
C. less debt a firm has per dollar of total assets.
D. number of outstanding shares of stock increases.
E. accounts payable balance decreases.
Difficulty: 1 Easy
Topic: Financial and operating leverage
Learning Objective: 02-01 Describe the difference between accounting value (or "book" value. and market value.
[单选题]4.A rough measure of the degree of economic interdependence of a nation is give n by:
A.A.the size of the nations' population
B.B.the percentage of its population to its GDP
C.C.the percentage of a nation's imports and exports to its GDP
D.D.all of the above
[单选题] "______?
Two degree on starboard.
A. What rudder
B. How heading
C. Are you on your course
D. How answer"
[单选题]Although the original budget for the project was one billion Yuan, ( ) the
Cost is likely to be 50% higher.虽然该项目原本的预算是10亿元,但最后可能会多出百分之50
A. locally
B. genuinely
C. similarly
D. eventually最后,终于
[单选题]Rossiter Restaurants is analyzing a project that requires $180,000 of fixed assets. When the project ends, those assets are expected to have an aftertax salvage value of $45,000. How is the $45,000 salvage value handled when computing the net present value of the project?
A. Reduction in the cash outflow at Time 0
B. Cash inflow in the final year of the project
C. Cash inflow for the year following the final year of the project
D. Cash inflow prorated over the life of the project
E. Excluded from the net present value calculation
Difficulty: 1 Easy
Topic: Net present value
Learning Objective: 09-01 Show the reasons why the net present value criterion is the best way to evaluate proposed investments.
[单选题]A project has a discounted payback period that is equal to the required payback period. Given this, the project:
A. will not be acceptable under the payback rule.
B. must have a profitability index that is equal to or greater than 1.0.
C. must have a zero net present value.
D. must have an internal rate of return equal to the required return.
E. will still be acceptable if the discount rate is increased.
Difficulty: 1 Easy
Topic: Discounted payback
Learning Objective: 09-03 Discuss the discounted payback rule and some of its shortcomings.
[单选题]Pro forma statements for a proposed project should generally do all of the following except:
A. be compiled on a stand-alone basis.
B. include all project-related fixed asset acquisitions and disposals.
C. include all the incremental cash flows related to the project.
D. include taxes.
E. include interest expense.
Difficulty: 1 Easy
Topic: Pro forma statements
Learning Objective: 10-01 Determine the relevant cash flows for a proposed project.
[单选题]Which one of the following methods of project analysis is defined as computing the value of a project based on the present value of the project's anticipated cash flows?
A. Constant dividend growth model
B. Discounted cash flow valuation
C. Average accounting return
D. Expected earnings model
E. Internal rate of return
Difficulty: 1 Easy
Topic: Net present value
Learning Objective: 09-01 Show the reasons why the net present value criterion is the best way to evaluate proposed investments.
[单选题]The fact that a proposed project is analyzed based on the project's incremental cash flows is the assumption behind which one of the following principles?
A. Underlying value principle
B. Stand-alone principle
C. Equivalent cost principle
D. Salvage principle
E. Fundamental principle
Difficulty: 1 Easy
Topic: Project analysis and evaluation
Learning Objective: 10-01 Determine the relevant cash flows for a proposed project.
[单选题]The net present value of a project will increase if:
A. the required rate of return increases.
B. the initial capital requirement increases.
C. some of the cash inflows are deferred until a later year.
D. the aftertax salvage value of the fixed assets increases.
E. the final cash inflow decreases.
Difficulty: 1 Easy
Topic: Net present value
Learning Objective: 09-01 Show the reasons why the net present value criterion is the best way to evaluate proposed investments.
[单选题]Which one of the following is a project cash inflow? Ignore any tax effects.
A. Decrease in accounts payable
B. Increase in accounts receivable
C. Decrease in inventory
D. Depreciation expense
E. Equipment acquisition
Difficulty: 1 Easy
Topic: Cash flows
Learning Objective: 10-01 Determine the relevant cash flows for a proposed project.
[单选题]A project has a required payback period of three years. Which one of the following statements is correct concerning the payback analysis of this project?
A. The cash flows in each of the three years must exceed one-third of the project's initial cost if the project is to be accepted.
B. The cash flow in Year 3 is ignored.
C. The project's cash flow in Year 3 is discounted by a factor of (1 + R.3.
D. The cash flow in Year 2 is valued just as highly as the cash flow in Year 1.
E. The project is acceptable whenever the payback period exceeds three years.
Difficulty: 1 Easy
Topic: Payback
Learning Objective: 09-02 Discuss the payback rule and some of its shortcomings.
[单选题]The cost of capital for a new project:
A. is determined by the overall risk level of the firm.
B. is dependent upon the source of the funds obtained to fund that project.
C. is dependent upon the firm's overall capital structure.
D. should be applied as the discount rate for all other projects considered by the firm.
E. depends upon how the funds raised for that project are going to be spent.
Difficulty: 1 Easy
Topic: Cost of capital - general
Learning Objective: 14-03 Determine a firm's overall cost of capital and how to use it to value a company.
[判断题]Premiere Pro中存放素材的窗口是Project窗口
A.正确
B.错误

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码