更多"[单选题]( )is aproject mangement techn"的相关试题:
[单选题]The life cycle of aproject is a description of the various phases of the project from thebeginning to the end. One of the followings is not a phase of the traditionalproject life cycle, It is( ).
A.development
B.concept
C.system analysis
D.implementation
[单选题]Quality?mangement ensures that an organization,product or service is consitent.It has four main components;quality planing,quality assurance( )and quatily improvenment.
A.quality obiective
B.quality policy
C.quality control
D.quality system
[单选题]( )is a project management technique for measuring projectPerformance progress.It has the ability to combine measurements of the project management triangle: scope,time and costs.
A.Critica1 path method(CPM)
B.Earned value management(CEV)
C.Net present value method(NPVM)
D.Expert judgment method(EJM)
[单选题]The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ) .
A.he project is ahead of its planned schedule
B.less work was completed than was planned t
C.the cost overrun for work completed
D.the cost underrun of performance to date
[单选题]The () technique involves using project characteristics in a mathematical modelto predict total project costs. Models can be simple or complex.
A.Cost Aggregation
A.Reserve Analysis
B.Parametri
C.Estimating
D.Funding Limit Reconciliation
[单选题]( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.
A.Parametric
B.Analogous
C.Three-point
D.Expert judgment
[单选题]()is a technique for estimating the duration or cost of activity or a projecy using historical data orm a similar activity or project.
A.Analogous estimating
B.Parametric estimating
C.Three-Point estmating
D.Bottom-Up estimating
[单选题]( )is a project management technique for measuring project performance and process. It has the ability to combine measurements of the project management triangle; scope time and costs.
A.Critica path method(CPM)
B.Earned value mangagemengt(EVM)
C.Net present value method(NPVM)
D.Expert judgment method(EJM)