更多"An output of scope definition is __"的相关试题:
[单项选择]Scope definition is ______ .
A. the process of developing a detailed project scope statement as the basis for future project decisions
B. determining the responses needed to perform project activities
C. analysis of activity sequence, duration, and resource requirements
D. a written statement identifying the quality standards relevant to the project
[单项选择]Completion of project scope activities is not measured against the ______ .
A. scope statement
B. requirements
C. WBS dictionary
D. WBS
[单项选择]What is the definition of tribalism
A. Sharing among members of the extended family.
B. Giving a job to a fellow tribesman.
C. A force that can be both good and bad.
D. People have the same religious belief.
[单项选择]While expanding the scope of bills eligible for discount, the ceiling on discount interest rate will be, gradually increased in support of the market - based interest rate reform.
[单项选择]During a project the scope of a product purchased on a cost reimbursable contract has increased.In the contract the fee to cover the contractor's indirect costs and allow a profit is calculated as 20% of the direct costs.What is most likely to be true ?()
A. The contractor's indirect costs will increase and the customer's payment for them will increase,to
B. The contractor's indirect costs will increase but the eLlstomer's payment for them will not increas
C. Neither the contractor's indirect costs nor the customer's payment for them will increas
D. The contractor's indirect costs will not increase but the customer's payment for them will increas
[单项选择]According to covering scope, which three classes can computer network be divided A) PSN, LAN, WANB) MAN, LAN, WAN C) PSN, FAST Ethernet, LAN D) PSN, FAST Ethernet, MAN
A. Receive Ready
B. Receive not Ready
C. Reject
D. Selective Reject
[单项选择]Inputs used during scope planning include all of the following EXCEPT ______ .
A. constraints
B. project charter
C. budget/cost analysis
D. product description
[单项选择]During the project scope planning process, the work breakdown structure should be developed to ______ .
A. the sub-project level
B. the level determined by the project office
C. a level allowing for adequate estimates
D. the cost center level
[单项选择]Verify scope ______ .
A. is the process of obtaining the stakeholders formal acceptance of the completed project scope and associated deliverables
B. refers to the final project report describing the project at completion
C. is not necessary if the project completes on time and on budget
D. OCCURS only when revisions of change orders are made to the project
[单项选择]The purpose of the scope statement includes all but which of the following:
A. Provides a basis for future project decision
B. Establishes a contract between the project team and the custome
C. Sets criteria to use to determine if a project or phase have been completed successfull
D. Establishes project constraints and assumption
[单项选择]Scope change control MUST be integrated with all of the following control processes EXCEPT ______ .
A. schedule
B. cost
C. procurement
D. quality
[单项选择]In scope and difficulty, the canals construction was most closely alike to that of the ______. ( )
A. Suez Canal
B. trans-Siberian Railroad
C. Taj Mahal
D. pyramids of Egypt
[单项选择]What is the definition of a Path
A. A sequence of vertices and the edges formed by each successive pair of vertice
B. A walk with distinct vertice
C. A walk with distinct edge
D. None of the above
[单项选择]What is the definition of a path
A. A sequence of vertices and the edges formed by each successive pair of vertice
B. A walk with distinct vertice
C. A walk with distinct edge
D. None of the above
[单项选择]What is implied about the scope of business of Qantas
A. Fashion design.
B. Dealing with stocks
C. Airlines
D. Shipping
[单项选择]The scope of freight forwarder’s service on behalf of consignee (CIF) includes( ).
A. packing the goods
B. paying the freight to the marine carrier
C. arranging import customs clearance
D. booking space with the marine carrier