[单项选择]During a project the scope of a product purchased on a cost reimbursable contract has increased.In the contract the fee to cover the contractor's indirect costs and allow a profit is calculated as 20% of the direct costs.What is most likely to be true ?()
A. The contractor's indirect costs will increase and the customer's payment for them will increase,to
B. The contractor's indirect costs will increase but the eLlstomer's payment for them will not increas
C. Neither the contractor's indirect costs nor the customer's payment for them will increas
D. The contractor's indirect costs will not increase but the customer's payment for them will increas

更多"During a project the scope of a pro"的相关试题:

[单项选择]During the project scope planning process, the work breakdown structure should be developed to ______ .
A. the sub-project level
B. the level determined by the project office
C. a level allowing for adequate estimates
D. the cost center level
[单项选择]Inputs used during scope planning include all of the following EXCEPT ______ .
A. constraints
B. project charter
C. budget/cost analysis
D. product description
[单项选择]Completion of project scope activities is not measured against the ______ .
A. scope statement
B. requirements
C. WBS dictionary
D. WBS
[单项选择]What may the project team do to confirm the scope of the project is on track
A. Review change requests that have been submitted and approve
B. Obtain status from responsible individuals on the tea
C. Conduct walkthrough, inspections and review
D. Complete a scope report and submit it to managemen
[单项选择]During project execution,the customer authorizes and funds a scope change which requires a major change in the schedule.The baseline schedule ().
A. now becomes the new schedule,including the changes,and the original baseline is disregarded
B. is still the original baseline but annotated to reflect that a change has taken place
C. is amended to reflect the scope change,but the original baseline is still maintained for post-project review
D. is meaningless since every schedule update changes the baseline
[单项选择]During initiation, a project manager is planning the upcoming project execution team meetings. What should the project manager include in these meetings that would have the biggest impact on the project
A. Review of the action item lis
B. Review of identified risk
C. Assignment of tasks to team member
D. Estimating cost
[单项选择]During the execution phase of project,you realize that one of the product functionalities has been omitted in the project plan,which will not eventually satisfy the requirement,you should ().
A. update the project schedule and budget
B. submit a change request to change control board and re-baseline
C. negotiate with the client for a new delivery date based on the revised schedule
D. informing management and take necessary measures for changes in budget and schedule
[单项选择]Scope planning for a project is ______ .
A. the project specification that includes design principles and project objectives
B. a three-level project work breakdown structure
C. the process of creating a project scope management plan
D. the record showing that all project deliverables are completed satisfactorily
[单项选择]During project execution, a new ISO version of standard 9000 is issued. The project team meets with the quality department to determine how the standard will apply to the project. Which part of the quality process is this
A. Quality analysi
B. Quality assuranc
C. Quality contro
D. Quality plannin
[单项选择]In your project, you use product analysis to translating project objectives into tangible deliverables and requirements. All the following tools are used for product analysis EXCEPT ______ .
A. value engineering
B. value analysis
C. product breakdown
D. benefit/cost analysis
[单项选择]The project manager can enhance project communications and team building by doing all the following except______.
A. having a“war room”
B. being a good communication blocker
C. being a communication expeditor
D. holding effective meetings
[单项选择]The company purchased several computers programmed to ______ the specific tasks required.
A. tackle
B. solve
C. assign
D. follow
[单项选择]An administrator has purchased monitoring software that can be configured to send alerts when hardware and applications are having issues. Which of the following must be installed on the monitoring server so that it can properly monitor details on vendor specific devices?()
A. MIBs
B. SMTP
C. WMI
D. DHCP
[单项选择]The project sponsor has just provided the project charter.What is the NEXT thing to do ?()
A. Begin to complete work package
B. Complete scope verificatio
C. Start integrated change contro
D. Start to create management plan
[单项选择]In considering project stakeholders, the project management team must do all of the following EXCEPT:
A. As much as possible, create conflicts among stakeholders to allow the project team to get its work don
B. Identify the stakeholder
C. Determine stakeholders requirements and expectation
D. To the extent possible, manage stakeholders influence in relation to the requirements to ensure a successful projec
[单项选择]While completing a project a project manager realizes be needs to decrease project costs. After researching his options, he comes up with the following choices. Which choice would DECREASE project costs ?()
A. Change to component A from component Component A costs more to purchase but has a lower life cycle cost than
B. Change task A to be completed by resource B instead of Resource C, Resource B is a more experienced worke
C. Move tasks B and H to occur concurrently, and take the risk of a 30% increase in the need for five more resources late
D. Remove a test from the project pla

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码