[单项选择]Scope planning for a project is ______ .
A. the project specification that includes design principles and project objectives
B. a three-level project work breakdown structure
C. the process of creating a project scope management plan
D. the record showing that all project deliverables are completed satisfactorily

更多"Scope planning for a project is ___"的相关试题:

[单项选择]During the project scope planning process, the work breakdown structure should be developed to ______ .
A. the sub-project level
B. the level determined by the project office
C. a level allowing for adequate estimates
D. the cost center level
[单项选择]Completion of project scope activities is not measured against the ______ .
A. scope statement
B. requirements
C. WBS dictionary
D. WBS
[单项选择]During a project the scope of a product purchased on a cost reimbursable contract has increased.In the contract the fee to cover the contractor's indirect costs and allow a profit is calculated as 20% of the direct costs.What is most likely to be true ?()
A. The contractor's indirect costs will increase and the customer's payment for them will increase,to
B. The contractor's indirect costs will increase but the eLlstomer's payment for them will not increas
C. Neither the contractor's indirect costs nor the customer's payment for them will increas
D. The contractor's indirect costs will not increase but the customer's payment for them will increas
[单项选择]Inputs used during scope planning include all of the following EXCEPT ______ .
A. constraints
B. project charter
C. budget/cost analysis
D. product description
[单项选择]A project planning methodology is any structured approach used to guide the project team during development of the project plan. What is an example of this methodology
A. Standard forms or template
B. Upper management involvemen
C. Functional work authorization
D. Stakeholders skill
[单项选择]Having the client assist in the project planning ______ .
A. is not always recommended since the client does not have adequate knowledge of project management
B. enables better planning since they are familiar with project insights
C. provides only some understanding, but usually the client dealing with the project has only limited authority
D. usually confuses the situation
[单项选择]During initiation, a project manager is planning the upcoming project execution team meetings. What should the project manager include in these meetings that would have the biggest impact on the project
A. Review of the action item lis
B. Review of identified risk
C. Assignment of tasks to team member
D. Estimating cost
[单项选择]What may the project team do to confirm the scope of the project is on track
A. Review change requests that have been submitted and approve
B. Obtain status from responsible individuals on the tea
C. Conduct walkthrough, inspections and review
D. Complete a scope report and submit it to managemen
[单项选择]The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.
A. work performance information
B. scope statement
C. change requests
D. process analysis
[单项选择]The project manager can enhance project communications and team building by doing all the following except______.
A. having a“war room”
B. being a good communication blocker
C. being a communication expeditor
D. holding effective meetings
[单项选择]In quality planning:
A. The primary benefit of meeting quality requirements is the reduced expense associated with project quality management activitie
B. Cost-benefits tradeoffs must be considere
C. The primary cost of meeting quality requirements is increased rewor
D. Benefits cannot be evaluated in relation to cost
[单项选择]The project sponsor has just provided the project charter.What is the NEXT thing to do ?()
A. Begin to complete work package
B. Complete scope verificatio
C. Start integrated change contro
D. Start to create management plan
[单项选择]In considering project stakeholders, the project management team must do all of the following EXCEPT:
A. As much as possible, create conflicts among stakeholders to allow the project team to get its work don
B. Identify the stakeholder
C. Determine stakeholders requirements and expectation
D. To the extent possible, manage stakeholders influence in relation to the requirements to ensure a successful projec
[单项选择]While completing a project a project manager realizes be needs to decrease project costs. After researching his options, he comes up with the following choices. Which choice would DECREASE project costs ?()
A. Change to component A from component Component A costs more to purchase but has a lower life cycle cost than
B. Change task A to be completed by resource B instead of Resource C, Resource B is a more experienced worke
C. Move tasks B and H to occur concurrently, and take the risk of a 30% increase in the need for five more resources late
D. Remove a test from the project pla
[单项选择]About midway through the project,the project manager learns that most members of the project team do not review the weekly project updates.What should the project manager do
A. Great a signature log do team members can indicate when they have read the report
B. Revise the communications plan appropriately to meet the information needs of the stakeholder
C. Improve the layout of the weekly project updates to encourage reading by team member
D. Go to the team members first hand to inquire why they are not reading the report
[单项选择]Being the project manager in a software project which is currently initiated,you want to assess high level risks.What should you do ?()
A. Develop a preliminary scope statement and document initially identified risks in this documen
B. Identify and analyze risk events using qualitative and quantitative technique
C. Develop contingency plans and fallback plans in case the original plan proves Wron
D. Discuss the risks documented in your risk register with the project key stakeholder
[单项选择]The project charter is created in which project management process group ?()
A. Executin
B. Plannin
C. Closin
D. Initiatin
[单项选择]The project charter for a project was approved for planning and you have Just been assigned as project manager.Realizing that project planning is an ongoing effort throughout the project,which processes are you MOST likely to combine ?()
A. Create WBS and activity definitio
B. Activity duration estimating and schedule developmen
C. Human resource planning and cost estimatin
D. Cost estimating and cost budgetin
[单项选择]Being assigned as the project manager to a project you perform earned value Analysis and find the following results:EV=250000;PV=200000;AC=275000;BAC=500000.What is right ?()
A. EAC=400000
B. EAC=550000
C. BTC=400000
D. ETC=75000

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码