[单项选择]The project charter is created in which project management process group ?()
A. Executin
B. Plannin
C. Closin
D. Initiatin

更多"The project charter is created in w"的相关试题:

[单项选择]You have created the project charter but could not get it approved. Your manager and his boss asked that the project begin immediately. Which of the following is the BEST thing to do
A. Set up an integrated change control proces
B. Push to get the charter signe
C. Perform an impact analysi
D. Start work on only the critical path task
[单项选择]The project charter for a project was approved for planning and you have Just been assigned as project manager.Realizing that project planning is an ongoing effort throughout the project,which processes are you MOST likely to combine ?()
A. Create WBS and activity definitio
B. Activity duration estimating and schedule developmen
C. Human resource planning and cost estimatin
D. Cost estimating and cost budgetin
[单项选择]When developing the project charter, any kind of the organzation's enterprise environmental factors must be considered. This may include the following EXCEPT______.
A. company reputation
B. personnel administration procedure, including training records
C. existing facilities and capital equipment
D. stakeholder risk tolerances
[单项选择]What is the purpose of a project charter ?()
A. To address and document the characteristics and boundaries of the project and its associated products and service
B. To formally authorize the project and provide the project manager with the authority to apply organizational resource
C. To link the project,which is going to be planned,executed,and monitored/controlled to the ongoing work of the organizatio
D. To break down the scope of the project into smaller,better manageable components for further planning and estimatin
[单项选择]Why is it important to have a project charter ?()
A. It is the collection of all subsidiary project document
B. The project charter is the necessary basis for all work packages to be performe
C. It formally authorizes the projec
D. It tracks the progress of the projec
[单项选择]Which of the following BEST describes a project management plan ?()
A. A print out from project management softwar
B. A bar char
C. Risk management,staffing,process improvement and other management plan
D. The project scop
[单项选择]Project Hond Start which was inaugurated in the United States in 1965 is a federally funded preschool for economically and culturally disadvantaged children.
A. initiated
B. celebrated
C. installed
D. proposed
[单项选择]You are the project manager of a new project,which will construct a bridge on the River Nile in Egypt.Before initiating the project,you should ().
A. create a scope management plan to document:how the project scope will be defined,verified and controlled
B. develop a project management plan
C. determine specific activities that need to be performed to produce the various project deliverables
D. facilitate the formal authorization to start a new project
[单项选择]There is supposed to be a safety ________ which makes it impossible for trains to collide.
A. appliance
B. accessory
C. machine
D. mechanism
[单项选择]Which of the following standard charter pany forms is used in a voyage charter.( )
A. GENCON
B. BALTIME
C. NYPE
D. BARECON
[单项选择]Which of the following standard Charter Party forms is used in a Voyage Charter ( )
A. GENCON
B. BALTIME
C. NYPE
D. BARECON
[单项选择]A stored procedure object is created into which DB2 object?()
A. Alias
B. Schema
C. Package
D. Routine Space
[单项选择]In your project,you have created performance reports to provide the status and progress information to different stakeholders.The results from the performance reports should be compared to the______.
A. project management plan
B. performance measurement baseline
C. earned value calculations
D. none of the above
[单项选择]A detailed project schedule can be created only after creating the ().
A. project budget
B. work breakdown structure
C. project management plan
D. detailed risk assessment
[单项选择]A trigger can be created on which of the following objects?()
A. View
B. Catalog Table
C. Stored Procedure
D. Global Temporary Table
[单项选择]Which of the following charter forms is used in a voyage charter. ( )
A. GENCON
B. BALTIME
C. NYPE
D. BARECON
[单项选择]Your management is evaluating a project which requires an investment of $500,000. The expected inflow is $100,000 for 1st year, and $300,000 for every year after that. What is the payback period
A. 2 year
B. 2 years and 4 month
C. 3 year
D. Cannot be determined because discount rate is not specifie
[单项选择]Which project management process group normally takes the MOST project time and resources
A. Plannin
B. Desig
C. Integratio
D. Executio
[单项选择]Which of the following technologies was created to reduce cost, increase cable length, and uses 3.3v across the line?()
A. Wide-Ultra2 SCSI-3
B. High-Voltage Differential
C. Low-Voltage Differential
D. Fibre Channel

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码