[单项选择]During the execution phase of project,you realize that one of the product functionalities has been omitted in the project plan,which will not eventually satisfy the requirement,you should ().
A. update the project schedule and budget
B. submit a change request to change control board and re-baseline
C. negotiate with the client for a new delivery date based on the revised schedule
D. informing management and take necessary measures for changes in budget and schedule

更多"During the execution phase of proje"的相关试题:

[单项选择]During project execution,the customer authorizes and funds a scope change which requires a major change in the schedule.The baseline schedule ().
A. now becomes the new schedule,including the changes,and the original baseline is disregarded
B. is still the original baseline but annotated to reflect that a change has taken place
C. is amended to reflect the scope change,but the original baseline is still maintained for post-project review
D. is meaningless since every schedule update changes the baseline
[单项选择]At the beginning of project execution,you notice different opinions between team members relating to project work and deliverables and to the level of overall complexity.What should you do right now ?()
A. Give your team members some time to develop a common understanding of the project scope and product scopUpcoming interface problems may be resolved late
B. Use the risk management processes to identify and assess risks caused by misunderstandings and develop a plan with measures in order to respond to the
C. Organize meetings to identify and resolve misunderstandings between team members in order to early avoid interface problems,disintegration and costly rewor
D. Use interviews in private with each individual team member to inform them of your expectations and your requirements in an atmosphere of confidenc
[单项选择]During project execution, a new ISO version of standard 9000 is issued. The project team meets with the quality department to determine how the standard will apply to the project. Which part of the quality process is this
A. Quality analysi
B. Quality assuranc
C. Quality contro
D. Quality plannin
[单项选择]You never realize how fortunate you are to have good health until it is suddenly brought home to you by the sight of suffering.
A. 除非你突然亲眼目睹体弱多病之苦,不然,你不会队识到你有一个健康的身体是何等幸运。
B. 你永远不会意识到拥有健康是多么幸运,除非健康光临你家。
C. 除非健康和苦难同时降临你家,否则,你不会幸运的。
D. 你从来不知道拥有健康是多么幸运。直到有一天,疾病突然降临,你才如梦方醒。
[单项选择]During which phase is a proposal developed and delivered? ()
A. Prepare
B. Plan
C. Design
D. Operate
[单项选择]During which phase of the boot process is the rootvg volume group varied on and the root file system (hd4) checked?()
A. Boot phase 1
B. Boot phase 2
C. Boot phase 3
D. Boot phase 4
[单项选择]"You realize that you were driving at 100mph, don't you " "No, officer, I {{U}}may not{{/U}} have been. This car can't do more than 80."
A. will not
B. cannot
C. might not
D. could not
[单项选择]When you appreciate Tang poetry you'll realize that true poetry ______ meaning every time it is read.
A. leaps
B. bounds
C. increases
D. accumulates
[单项选择]In which project phase do you have the GREATEST influence on project risk
A. Conceptua
B. Desig
C. Executio
D. Implementatio
[单项选择]During the examination you are supposed to stay in your seats, to keep your eyes on your papers, ______ to anyone.
A. but could not talk
B. not talk
C. and not to speak
D. rather than
[单项选择]In your project, you realize the importance of determining the start and finish dates for project activities. If the project start or end dates are not realistic, then the project may not be completed on time. This is done as part of ______ .
A. activity sequencing
B. activity duration estimating
C. schedule development
D. activity definition
[单项选择]You realize that the control file is damaged in your production database.After restoring the control file from autobackup, what is the next step that you must do to proceed with the database recovery?()
A. Mount the database
B. Open the database in NORMAL mode
C. Open the database in RESTRICTED mode
D. Open the database with the RESETLOGS option
[单项选择]During activity sequencing,you identify and document interactivity dependencies.All the following are outputs from activity sequencing process EXCEPT ().
A. project schedule network diagrams
B. activity attribute updates
C. requested changes
D. milestone list
[单项选择]Hide behind the cubes during an attack you can ______.
A. let them shoot over you without any danger
B. be certain of hitting your target(靶子)
C. easily shoot from behind them
D. fire straight at your enemy
[单项选择]During the office hours, you should {{U}}focus your mind on{{/U}} your work.
A. concentrate on
B. complete
C. remind
D. pap for
[单项选择]At the first phase end of the project, you should ensure that ______ before you begin the next phase.
A. resource are available for the next phase
B. progress was achieved to its baseline
C. corrective actions are taken to bring project results
D. the phase has achieved the objectives and formally accepts its deliverables

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码