题目详情
当前位置:首页 > 职业培训考试
题目详情:
发布时间:2023-09-28 14:25:11

[单项选择]While working on an external project your customer asks you to perform some additional tasks that are not included in the formal contract.You should ().
A. honor the customer's request as sign of cooperation to ensure future business
B. refuse the request and report the customer to your sponsor
C. acknowledge the request and advise the customer to submit a formal change request
D. convene a meeting of the project team and rewrite the scope statement

更多"While working on an external projec"的相关试题:

[单项选择]You are working in the project office of your organization. What is your job responsibility
A. Managing the operational activities in the compan
B. Always managing human resource and risk management issues for project
C. Central coordination of communication management across project
D. Providing subject matter expertise in the functional areas of the projec
[单项选择]While implementing your project,a team member brings to your notice a risk that was not mentioned in the risk response plan.In this case,you should______.
A. accept the risk
B. perform additional risk response planning to control the risk
C. inform the project sponsor
D. use project contingency
[单项选择]While completing a project a project manager realizes be needs to decrease project costs. After researching his options, he comes up with the following choices. Which choice would DECREASE project costs ?()
A. Change to component A from component Component A costs more to purchase but has a lower life cycle cost than
B. Change task A to be completed by resource B instead of Resource C, Resource B is a more experienced worke
C. Move tasks B and H to occur concurrently, and take the risk of a 30% increase in the need for five more resources late
D. Remove a test from the project pla
[单项选择]Your schedule analysis has shown that your project has a high likelihood of experiencing a schedule overrun. You know this because the cumulative EV is much ______ .
A. higher than the cumulative AC
B. higher than the cumulative PV
C. lower than the cumulative PV
D. lower than the cumulative CPI
[单项选择]Charles is working on a project and finds that one of his primary vendors is raising their costs for a key component of the product being produced by his project.In order to cover these costs,he______.
A. will ask management for a budget increase to cover the difference
B. will assume management reserve will cover the difference because this increase was out of his control
C. will use the cost change control process to obtain approval to use part of the contingency allowance
D. will go over budget and ask for forgiveness at the end of the project Charles
[单项选择]The project team is working on an important and complex project that requires a lot of coordination.Under these circumstances,the BEST strategy is to______.
A. have a war room
B. hire a contractor
C. hold more meetings to get the word out
D. gain extra assistance from management
[单项选择]While doing calculation for the project, the designers ______ a new solution to a geological problem.
A. fell into
B. stumbled upon
C. set out
D. discovered
[单项选择]-I am still working on my project. -Oh, you'll miss the deadline. Time is ______.
A. running out
B. going out
C. giving out
D. losing out.
[单项选择]Let's start working on the project, ______
[单项选择]() he is still working on the project, I don't mind when he will finish it.
A. In case
B. As long as
C. Even if
D. As far as
[单项选择]In your project,you use the“develop project team”process to improve the competencies and interaction of team members to enhance project performance. The outputs from this process are ().
A. project staff assignments
B. team performance assessment
C. staffing management plan
D. project staff assignments,staffing management plan,team performance assessment
[单项选择]While evaluating the Gantt chart,the project manager determines that the project is behind schedule.What should she do ?()
A. Obtain approval from the customer to slip the projec
B. Report findings to managemen
C. Evaluate the alternatives with the tea
D. Evaluate the alternatives with the custome
[单项选择]______ he is still working on the project, I don't mind when he will finish it.
A. In case
B. As long as
C. Even if
D. As far as
[单项选择] _______he is still working on the project, I don''t mind when he will finish it.
A. In case
B. As long as
C. Even if
D. As far as
[单项选择]In your software development project you have planned for system testing from March 1st and the duration is 10 days.Two days before the completion of the system test,you can start the user acceptance test.The 2 days in this case is an example of ().
A. lead
B. lag
C. delay
D. float

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码