[单项选择]The project team is working on an important and complex project that requires a lot of coordination.Under these circumstances,the BEST strategy is to______.
A. have a war room
B. hire a contractor
C. hold more meetings to get the word out
D. gain extra assistance from management

更多"The project team is working on an i"的相关试题:

[单项选择]A project management team is evaluating the causes that might contribute to unsatisfactory performance and quality.Which of the following statements is not true ?()
A. Normal process variation is attributable to random causes and sometimes also called“white noise”.
B. Special causes are easier to predict and handle than random causes(also called common caus
C. Special causes are unusual events which are difficult to foresee and mostly produce outlier
D. A process can be optimized to limit the bandwidth of variations due to random cause
[单项选择]A project management team has subcontracted work to a service company.Which of the following tools is the best choice to assure that this company will be able to meet the quality requirements of the project ?()
A. Quality audi
B. Deliverable inspectio
C. Fixed price contrac
D. Service level agreemen
[单项选择]A project management team wants to procure some customized products which are available in identical grade and quality from many vendors.What should be included in the procurement package to ensure that their offers will be comparable ?()
A. A statement of work describing the needs of the project in sufficient detail to enable vendors to make suitable proposal
B. A statement of work specifying attributes and metrics of the requested deliverables in detal to allow vendors Submission of bid
C. The approved project scope statement,the WBS which should be broken down to work package level and the WBS dictionar
D. The risk management plan and the reports from those risk management reviews which have been made so fa
[单项选择]A project team is suffering from misunderstandings between team members who have different cultural backgrounds.The project manager is evaluating how to improve communication and collaboration.Which of the following statements is not true ?()
A. Only those who realize that cultural differences are a resource to be fully utilized will survive in international project busines
B. There is a common ground for people from different cultures on which they can interact without unsolvable conflict
C. Cultural differences will always remain an obstacle to be overcome for cross-cultural project
D. Cross-cultural competence is a critical lever for competitive advantage in international project busines
[单项选择]In your project,you use the“develop project team”process to improve the competencies and interaction of team members to enhance project performance. The outputs from this process are ().
A. project staff assignments
B. team performance assessment
C. staffing management plan
D. project staff assignments,staffing management plan,team performance assessment
[单项选择]Project team members are drawn from all available sources, both internal and external. When the project management team is able to influence or direct staff assignments, characteristics to consider include all of the following EXCEPT ______ .
A. availability
B. political philosophy
C. ability
D. experience
[单项选择]To ensure the project team provides the functionality the customer expects in a new piece of software, the project manager asks the customer for sign-off on the design criteria. These documents are ______ .
A. technical specifications
B. performance specifications
C. product descriptions
D. quality assurance
[单项选择]The project team has added some additional functionality which was not required as part of the project. However the customer is satisfied with the project. From a quality perspective, ______ .
A. this is high quality because it exceeded customer expectations
B. this is not acceptable quality because gold plating was done which is not advisable
C. this will mean repeat business from the same customer
D. none of the above
[单项选择]Tools and techniques to acquire the project team include all of the following EXCEPT ______ .
A. pre-assignment
B. acquisition
C. staffing management plan
D. negotiation
[单项选择]The project team has just completed the initial project schedule and budget.The NEXT thing to do is ().
A. begin risk identification
B. begin iterations
C. determine communications requirements
D. create a bar(Gantchart
[单项选择]The PM and the project team have completed decomposition and have verified scope, when the marking department makes a minor change to the product functionality to improve its appeal to the end customer. The PM and the project team ______ .
A. refuses to accept the change since the scope has been verified
B. modifies the WBS and the decomposition
C. accepts the change and incorporates it into the WBS, modifying the budget and the schedule and assigning accountability to the marking team
D. proceeds per the change process
[单项选择]A project team includes five people,then the project manager adds two more.How many additional channels of communication are there
A. 7.
B. 10.
C. 21.
D. 11.
[单项选择]The project team members should also be aware of one of the fundamentaltenets of modern quality management: quality is planned ,designed and built in,not (72 ).
A. executed in
B. inspected in
C. check-in
D. look-in
[单项选择]What may the project team do to confirm the scope of the project is on track
A. Review change requests that have been submitted and approve
B. Obtain status from responsible individuals on the tea
C. Conduct walkthrough, inspections and review
D. Complete a scope report and submit it to managemen
[单项选择]While implementing your project,a team member brings to your notice a risk that was not mentioned in the risk response plan.In this case,you should______.
A. accept the risk
B. perform additional risk response planning to control the risk
C. inform the project sponsor
D. use project contingency
[单项选择]Management of the project team is complicated ______ .
A. when team members are co-located
B. when minor problems do not impact the project completion date OE budget target
C. when team members are accountable to both a functional manager and the project manager
D. when formal training plans are implemented
[单项选择]In a project, two team members were using different versions of WBS. Team members could not know the status of project management plan documents. Project manager should FIRST check______.
A. configuration management system
B. work performance information
C. change control system
D. information gathering and retrieval systems
[单项选择]Why are the minutes of meetings important for a company
A. They provide a clear history of the firm and its evolution.
B. They concentrate scattered memos and directives in one synthetic document.
C. They reflect decision-making and control over company life.
D. They record any individual disagreements with company decisions.

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码