[单项选择]The WBS,estimates for each work package,and the network diagram are completed.Which of the following would be the NEXT thing for the project manager to do ?()
A. Sequence the activitie
B. Verify that they have the correct scop
C. Create a preliminary schedule and get the team's approva
D. Complete risk managemen

更多"The WBS,estimates for each work pac"的相关试题:

[单项选择]A work breakdown structure (WBS) numbering system should allow project staff to ______ .
A. identify the level at which individual WBS elements are found
B. identify configuration management milestones
C. estimate the costs of WBS elements
D. provide project justification
[单项选择]The creation of a work breakdown structure (WBS) is the process of ( )the major project deliverables.
A. subdividing
B. assessing
C. planning
D. integrating
[单项选择]( )(Project Dragram,或称WBS Work Breakdown Structure)是一个组织工具,它通过树状图的方式对一个项目的结构进行逐层分解,以反映组成该项目的所有工作任务。
A. 组织结构图
B. 项目结构图
C. 工作任务分工表
D. 工作流程图
[单项选择]We ______ 5 hours writing the plan for our work next month.
A. cost
B. spent
C. took
D. spare
[单项选择]I think my problems at work ____the fact that I never really wanted to go into accountancy as a career.
A. bring back
B. stir up
C. lie behind
D. spring from
[单项选择]{{U}}Because our work is very busy{{/U}}, so we need to relax at midday.
A. We are very busy,
B. Our work being busy,
C. Our work so very busy,
D. Because our work so very busy,
[单项选择]What is the WBS typically used for
A. To organize and define the total scope of the projec
B. To identify the logical person to be project sponso
C. To define the level of reporting the seller provides the buye
D. As a record of when work elements are assigned to individual
[单项选择]Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.
A. independent resource
B. individual work load
C. work milestone
D. work package
[单项选择]创建WBS的输入包括()。
A. 项目管理计划
B. 成本估算
C. WBS模板
D. 项目范围管理计划
[单项选择]WBS的三个基本要素是()
A. 层次结构、编码、工作包
B. 层次结构、编码、报告
C. 编码、报告、工作包
D. 层次结构、报告、工作包
[单项选择]Which of the following is true about the WBS:
A. The WBS is another term for the Gantt char
B. Each descending level of the WBS represents an increasingly detailed definition of the project wor
C. Work not in the WBS is usually defined in the scope statement of the projec
D. The WBS shows only the critical path activitie
[单项选择] (39) 不属于制订WBS过程的功能。
A. 为提高项目成本、活动历时估算和资源估算的准确度建立基础
B. 定义绩效考核和控制的基准
C. 形成清晰的职责任命
D. 建立项目经理和项目干系人之间的沟通网络
[单项选择](39)不属于制定WBS 过程的功能。
A. 为提高项目成本、活动历时估算和资源估算的准确度建立基础
B. 定义绩效考核和控制的基准
C. 形成清晰的职责任命
D. 建立项目经理和项目干系人之间的沟通网络
[单项选择]()不是WBS的正确分解方法或结构。
A. 把主要的项目可交付物和子项目作为第一层
B. 在同一WBS层上采用不同的分解方法
C. 在不同WBS层上可采用不同的分解方法
D. 把项目生命期作为第一层,项目交付物作为第二层
[单项选择]下面关于 WBS的描述,错误的是( )。
A. WBS是管理项目范围的基础,详细描述了项目所要完成的工作
B. WBS最底层的工作单元称为功能模块
C. 树型结构图 WBS层次清晰、直观、结构性强
D. 比较大的、复杂的项目一般采用列表形式的 WBS表示
[单项选择]______不属于制定WBS过程的功能。
A. 为提高项目成本、活动历时估算和资源估算的准确度建立基础
B. 定义绩效考核和控制的基准
C. 形成清晰的职责任命
D. 建立项目经理和项目干系人之间的沟通网络
[单项选择]______不属于制订WBS过程的功能。
A. 为提高项目成本、活动历时估算和资源估算的准确度建立的基础
B. 定义绩效考核和控制的基准
C. 形成清晰的职责任命
D. 建立项目经理和项目干系人之间的沟通网络
[判断题]Optix WBS 1600G、OSN6800既支持DWDM也支持CWDM。

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码