更多"You are looking at the following da"的相关试题:
[单项选择]You are looking at the following data. Project A has a CPI of 0.8 and SPI of 1.2 and EV of 450. Project B has CPI of 1.2 and SPI of 0.8 and EV of 650. Which of the following statement is true ?()
A. Project B is performing better because it has a higher earned value
B. Project A has schedule slippage and project B is ahead of schedule
C. Crashing project A is a good option
D. Crashing project B is a good option
[简答题]Object
Describe a project you did while you were studying
[单项选择]You have recently appointed a project manager to handle a critical project in your organization. You want to provide the project manager with authority to apply organizational resources to project activities. Which document should you use ?()
A. Resource authorization document
B. Work breakdown structure
C. Project charter
D. Project scope statement
[简答题]part 2 & 3
Describe a project you did while you were studying
Should children have homework Why
Do High-school students need to have a lot of homework
Do college students have part time jobs Why
How do we learn from our job
Why some parents choose to let their children study at home
Do you believe in Chinese education
What are the disadvantages of not having a computer
[简答题]part 2 & 3Describe a project you did while you were studying
Should children have homework Why
Do High-school students need to have a lot of homework
Do college students have part time jobs Why
How do we learn from our job
Why some parents choose to let their children study at home
Do you believe in Chinese education
What are the disadvantages of not having a computer
[简答题]part 2& 3Describe a project you did while you were studying
Should children have homework Why
Do High-school students need to have a lot of homework
Do college students have part time jobs Why
How do we learn from our job
Why some parents choose to let their children study at home
Do you believe in Chinese education
What are the disadvantages of not having a computer
[简答题]Which of the following characteristic do you think is the most important infriendship, honesty, loyalty and humor 5 Z3 ^1 l, ^9 t9 w- f
[单项选择]You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you’ve spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule,you should have spent ¥300,000 by this point. Based on these circumstances, your project could be best described as ______.
A. ahead of schedule
B. behind schedule
C. on schedule
D. having not enough information provided
[单项选择]In which of the following situations will you find your image most vague
A. When looking into the mirror.
B. When lying in bed with closed eyes.
C. When standing.
D. When walking.
[简答题]Part 2&3a team project you joined
[单项选择]In your software development project you have to wait for 5 days after ordering a new software and then only you can start integration testing. The 5 days in this case is an example of ().
A. lead
B. lag
C. delay
D. float
[单项选择]In which of the following project phases is the project schedule developed
A. conceptual.
B. planning.
C. implementation.
D. design.
[单项选择]Which of the following statements best describes humor in China
a. It is more or less the same in all parts of the country.
b. It is drastically different in every part of the country.
c. It is distinguished from Hong Kong.
d. It is more a verbal act than a physical act in the north.