题目详情
题目详情:
发布时间:2024-02-02 00:06:14

[单项选择]Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.
A. analyze
B. track
C. level
D. extend

更多"Developing the project schedule is "的相关试题:

[单项选择]Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to ______ progress.
A. analyze
B. track
C. level
D. extend
[单项选择]For a well planned project the project schedule is ______.
A. the agenda for carrying out the plan or a portion of it
B. not important, as each team member acts according to plan
C. used to generate a time table of major commitments for the project
D. both A and C
[填空题]According to the schedule, the Project was originally planned to finish in February next year.
[单项选择]The method of constructing a project schedule network diagram that represents activities and connects then to show the all dependencies is known as ().
A. precedence diagramming method
B. activity list
C. arrow diagramming method
D. schedule network templates
[单项选择]A project schedule completion date will change if ().
A. the critical path is reduced
B. the contingency is no longer available
C. no float time is available
D. project resources are reduced
[单项选择]A manufacturing project has a schedule performance index(SPI)of 0.89 and a cost performance index(CPI)of 0.91.Generally,what is the BEST explanation for why this occurred ?()
A. The scope was changed
B. A supplier went out of business and a new one needed to be found
C. Additional equipment needed to be purchased
D. A critical path activity took longer and needed more labor hours to complete
[单项选择]A detailed project schedule can be created only after creating the ().
A. project budget
B. work breakdown structure
C. project management plan
D. detailed risk assessment
[单项选择]The high-level project schedule constraints have just been determined.What project management process group are you in ?()
A. Initiating
B. Planning
C. Executing
D. Monitoring and controlling
[单项选择]Your schedule analysis has shown that your project has a high likelihood of experiencing a schedule overrun. You know this because the cumulative EV is much ().
A. higher than the cumulative AC
B. higher than the cumulative PV
C. lower than the cumulative PV
D. lower than the cumulative CPI
[单项选择]The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to().
A. measure, delay, record, distribute, analyze, and direct
B. plan, schedule, monitor, control, report, and forecast
C. promote, highlight, monitor, control, forecast, and report
D. emphasize, visualize, analyze, conceptualize, report, and record
[单项选择]Long-married couples often schedule a weekly "date night"—a regular evening out with friends or at a favorite restaurant to strengthen their marital bond.
But brain and behavior researchers say many couples are going about date night all wrong. Simply spending quality time together is probably not enough to prevent a relationship from getting stale.
Using laboratory studies, real-world experiments and even brain-scan data, scientists can now offer longmarried couples a simple prescription for rekindling the romantic love that brought them together in the first place. The solution Reinventing date night.
Rather than visiting the same familiar haunts and dining with the same old friends, couples need to tailor their date nights around new and different activities that they both enjoy, says Arthur Aron, a professor of social psychology at the State University of New York at Stony Brook. The goal is to find ways to keep injecting novelty into the relationship. The activity c
A. It provides a way for long-married couples to improve their relationship.
B. It helps to explain why some couple’s passion for each other can last long.
C. It is the result of many means of scientific experiments.
D. It reveals that some couples are doing wrong when they date.

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码