更多"Developing the project schedule is "的相关试题:
[单项选择]Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.
A. analyze
B. track
C. level
D. extend
[单项选择]For a well planned project the project schedule is ______.
A. the agenda for carrying out the plan or a portion of it
B. not important, as each team member acts according to plan
C. used to generate a time table of major commitments for the project
D. both A and C
[填空题]According to the schedule, the Project was originally planned to finish in February next year.
[单项选择]The method of constructing a project schedule network diagram that represents activities and connects then to show the all dependencies is known as ().
A. precedence diagramming method
B. activity list
C. arrow diagramming method
D. schedule network templates
[单项选择]A manufacturing project has a schedule performance index(SPI)of 0.89 and a cost performance index(CPI)of 0.91.Generally,what is the BEST explanation for why this occurred ?()
A. The scope was changed
B. A supplier went out of business and a new one needed to be found
C. Additional equipment needed to be purchased
D. A critical path activity took longer and needed more labor hours to complete
[单项选择]Upon completing a project schedule, Roberta finds the critical path indicates the project will complete on April 15. As she works through the schedule, she finds there are several tasks with float. Task B has 10 days of free float, while Task F has 5 days of total float. If the start of Task B is delays, what is the completion date of the project
A. April 25.
B. Not enough information provided to calculat
C. April 20.
D. April 10.
[单项选择]The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to().
A. measure, delay, record, distribute, analyze, and direct
B. plan, schedule, monitor, control, report, and forecast
C. promote, highlight, monitor, control, forecast, and report
D. emphasize, visualize, analyze, conceptualize, report, and record
[单项选择]The high-level project schedule constraints have just been determined. What project management process group are you in
A. Initiating.
B. Planning.
C. Executing.
D. Monitoring and controlling.
[单项选择]A detailed project schedule can be created only after creating the ().
A. project budget
B. work breakdown structure
C. project management plan
D. detailed risk assessment
[单项选择]Long-married couples often schedule a weekly "date night"—a regular evening out with friends or at a favorite restaurant to strengthen their marital bond.
But brain and behavior researchers say many couples are going about date night all wrong. Simply spending quality time together is probably not enough to prevent a relationship from getting stale.
Using laboratory studies, real-world experiments and even brain-scan data, scientists can now offer long-married couples a simple prescription for rekindling the romantic love that brought them together in the first place. The solution Reinventing date night.
Rather than visiting the same familiar haunts and dining with the same old friends, couples need to tailor their date nights around new and different activities that they both enjoy, says Arthur Aron, a professor of social psychology at the State University of New York at Stony Brook. The goal is to find ways to keep injecting novelty into the relationship. The activity
A. To find their friends to chat in a cafe.
B. To have a walk and talk about their future plans.
C. To take a training class together.
D. To go to see a movie they, both enjoy.