[单项选择]

A project management technique that is currently in widespread use is the () . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activities called () , which are events that signify the accomplishment or completion of major deliverables during the project. Most system development methodologies also provide () , whose purpose is to contain the various pieces of relevant information – feasibility assessments, schedules, needs analysis, and so forth – in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management. ()was developed to make clear the interdependence between project tasks before those tasks are scheduled. () offers the advantage of clearly showing overlapping tasks.

A project management technique that is currently in widespread use is the ()
A. Functional decomposition diagram
B. Work Breakdown Structure
C. Structure Chart
D. Organizational Structure

更多"A project management technique that"的相关试题:

[单项选择]

A project management technique that is currently in widespread use is the () . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activities called () , which are events that signify the accomplishment or completion of major deliverables during the project. Most system development methodologies also provide () , whose purpose is to contain the various pieces of relevant information – feasibility assessments, schedules, needs analysis, and so forth – in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management. ()was developed to make clear the interdependence between project tasks before those tasks are scheduled. () offers the advantage of clearly showing overlapping tasks.

There are some special activities called ()
A. feasibility checkpoints
B. phases
C. iterations
D. milestones
[单项选择]Our management technique has been proven to be the most effective way to get into a target market and acquire potential customers.()
A. 我们的管理业务已经实现了市场目标,新客户也已获利,形势令人鼓舞。
B. 我们的管理理念是极为先进的,市场定位也是准确的,会赢得新的客户。
C. 我们的管理方法证明是非常有效的,可以实现市场目标并吸引更多客户。
D. 我们的管理技术业已证明是进入目标市场并获得潜在客户的最有效途径。
[单项选择]I Which project management process group is managing stakeholders in ?()
A. Initiating
B. Planning
C. Executing
D. Monitoring and controlling
[简答题]Describe how senior management and the statutory internal bodies of a company limited by shares promote ffective corporate governance. 10 marks)
[单项选择]Project integration management includes the processes and activities needed to identify, define, combine, unify and coordinate the various processes and project management activities. For successful project integration management, you should definitely have () (select the best option).
A. a strong matrix organizational structure in your company
B. a good communication management plan
C. good project selection techniques
D. positive stakeholders who support the project
[单项选择]In project management, a () is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events.
A. schedule
B. WBS
C. SOW
D. charter
[单项选择]A project management professional can compare earned value performance data to all of the following project management tools EXCEPT ______ .
A. critical path analysis
B. technical performance metrics
C. risk mitigation plans
D. forecasted final costs and schedule estimates
[单项选择]The competitive, complex project management environment has increased pressure for on-line performance Schedule control is one important way of avoiding schedule delay. Time management corrective action often involves expediting certain activities to ensure that they are completed in a timely manner or to ensure that they are completed with the least possible.delay. To plan and execute schedule recovery, corrective action frequently requires ______.
A. making unpopular decision
B. immediately re-baseline
C. root cause analysis
D. resource leveling
[单项选择]What is a project management information system
A. Computerized status tracking system.
B. Manual status tracking system.
C. Method to determine and archive how the project is doing.
D. Method to gather, integrate, and disseminate what and how the project is doing.
[单项选择]Project management techniques applied to ongoing operations is called as ().
A. portfolio management
B. management by projects
C. management by objectives
D. management by exception

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码