The inputs of developing project management plan do not include().
Project schedule management is made up of six management processes including:activity definition,activity sequencing()and schedule control by order.
The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to().
Your project is behind schedule due to conflict between team members.Having resolved the conflict,to get the project back on schedule,you should consider()