[单项选择]While working on an external project your customer asks you to perform some additional tasks that are not included in the formal contract.You should ().
A. honor the customer's request as sign of cooperation to ensure future business
B. refuse the request and report the customer to your sponsor
C. acknowledge the request and advise the customer to submit a formal change request
D. convene a meeting of the project team and rewrite the scope statement
[单项选择]Your schedule analysis has shown that your project has a high likelihood of experiencing a schedule overrun. You know this because the cumulative EV is much ______ .
A. higher than the cumulative AC
B. higher than the cumulative PV
C. lower than the cumulative PV
D. lower than the cumulative CPI
[单项选择]You are working in the project office of your organization. What is your job responsibility
A. Managing the operational activities in the compan
B. Always managing human resource and risk management issues for project
C. Central coordination of communication management across project
D. Providing subject matter expertise in the functional areas of the projec
[单项选择]In your project,you use the“develop project team”process to improve the competencies and interaction of team members to enhance project performance. The outputs from this process are ().
A. project staff assignments
B. team performance assessment
C. staffing management plan
D. project staff assignments,staffing management plan,team performance assessment
[单项选择]In your software development project you have planned for system testing from March 1st and the duration is 10 days.Two days before the completion of the system test,you can start the user acceptance test.The 2 days in this case is an example of ().
A. lead
B. lag
C. delay
D. float
[单项选择]Your plan about this project is excellent.
A. outstanding
B. wonderful
C. rare
D. so-so
[单项选择]Your management is evaluating a project which requires an investment of $500,000. The expected inflow is $100,000 for 1st year, and $300,000 for every year after that. What is the payback period
A. 2 year
B. 2 years and 4 month
C. 3 year
D. Cannot be determined because discount rate is not specifie
[单项选择]What is necessary for your query on an existing view to execute successfully?()
A. The underlying tables must have data.
B. You need SELECT privileges on the view.
C. The underlying tables must be in the same schema.
D. You need SELECT privileges only on the underlying tables.
[单项选择]In your project, some requested changes were generated from the activity definition process. These changes will be processed through ______ .
A. activity change control system
B. corrective action
C. integrated change control system
D. activity sequencing
[单项选择]Your project is behind schedule due to conflict between team members. Having resolved the conflict, to get the project back on schedule, you should consider ______ .
A. crashing the schedule
B. performing resource leveling
C. conducting reverse resource allocation scheduling
D. utilizing the critical chair resources
[单项选择]In your project,you have created performance reports to provide the status and progress information to different stakeholders.The results from the performance reports should be compared to the______.
A. project management plan
B. performance measurement baseline
C. earned value calculations
D. none of the above
[单项选择]You will complete your project more easily if you take ______ of all the facilities here.
A. privilege
B. advantage
C. chance
D. care
[单项选择]While implementing your project,a team member brings to your notice a risk that was not mentioned in the risk response plan.In this case,you should______.
A. accept the risk
B. perform additional risk response planning to control the risk
C. inform the project sponsor
D. use project contingency
[单项选择]In your software development project you have to wait for 5 days after ordering a new software and then only you can start integration testing.The 5 days in this case is an example of ().
A. lead
B. lag
C. delay
D. float
[单项选择]In your project, you realize the importance of determining the start and finish dates for project activities. If the project start or end dates are not realistic, then the project may not be completed on time. This is done as part of ______ .
A. activity sequencing
B. activity duration estimating
C. schedule development
D. activity definition
[单项选择]You are aware that an employee in your project may potentially get a promotion—however, there is a possibility that he may get transferred after his promotion, thus impacting your project. In this situation, you should:
A. Give a bad recommendation about the person so as to delay the promotion of the person until project is ove
B. Inform the employee about the potential promotion, and ask him to transition his responsibilities to another perso
C. After the employee gets the promotion and is told of the transfer, you ask him to prepare a transition pla
D. Hire another resource who can replace the person after he gets the promotio