更多"After project control, organization"的相关试题:
[单项选择]The schedule control process for a project ().
A. focuses on starting the project earlier than scheduled
B. is necessary for controlling changes to the project schedule
C. is concerned only with activities that are on the critical path
D. should focus entirely on activities that are difficult to carry out
[单项选择]
Perform Quality Control is the process of monitoring and recording results of executing the Quality Plan activities to assess performance and recommend necessary changes.()are the techniques and tools in performing quality control.
①Activity network diagram
②Cause and effect diagrams
③Inspection
④Flow chart
⑤Work Breakdown Structure
⑥Pareto chart
A. ①③⑤
B. ①②④⑥
C. ②③④⑤⑥
D. ①②③④⑥
[单项选择]The process control charts are used ().
A. to graph what typically focuses on the prevention of a problem
B. to detect the problem
C. to reject the problem
D. to determine the acceptability of the sample
[单项选择]The company formulated a package of______ for assessment of employees' performance.
A. criteria
B. partitions
C. principles
D. thresholds
[简答题]
Process Explanation
Process explanation is a description of an orderly process such as a math formula or a scientific technique. It often happens when someone encounters some difficulties in operating particular projects. There are two types of process explanation: directive explanation and informational explanation. Directive explanation is to directly demonstrate or tell people how to carry out a project step by step. Informational explanation means giving people a general idea about the project without presenting how to follow the instructions and finish the tasks accordingly.
Question: The professor gives his personal experience to illustrate the definition and two types of "process explanation". Explain how this example is related to the reading passage.
[单项选择]Capital budgeting process is the process of identifying and evaluating capital budgeting with four administrative steps. The most important step in the capital budgeting process is:()
A. forecasting cash flows.
B. generating good investment ideas.
C. analyzing individual proposals.
[简答题]介绍有关Cotton planting and process的负面影响
process
[单项选择]The upper and lower control limits in a control chart indicate that ().
A. boundaries the customer will accept
B. acceptable specification limits
C. acceptable range of variation in the process
D. statistical control points form judging the success or failure of the project
[名词解释]damage control othopedics
[填空题]After the film they went home by taxi.
After the film they ______ a taxi home.
[单项选择]
Configuration management is the process of managing change in hardware, software, firmware, documentation, measurements, etc. As change requires an initial state and next state, the marking of significant states within a series of several changes becomes important.The identification of significant states within the revision history of a configuration item is the central purpose of () identification.
A. baseline
B. value
C. cost
D. control
[单项选择]Which of the following process involves determining project roles, responsibilities, and reporting relationships, and develops the staffing management plan ?()
A. Manage project team.
B. Human resource planning.
C. Develop project team.
D. Acquire project team.
[单项选择]Which two process groups provide potentially cyclical inputs to each other
A. Executing processes and controlling processes.
B. Planning processes and executing processes.
C. Planning processes and controlling processes.
D. Controlling processes and closing processes.