[单项选择]
As an important phase in software development, software design is the continuation of software requirement analysis phase.
Ⅰ.software structure
Ⅱ.software procedure
Ⅲ.software module
Ⅳ.software document
which of the following should be included in software design phase ?()
A. Ⅰand Ⅱ
B. Ⅱand Ⅲ
C. Ⅰ,Ⅱ and Ⅲ
D. All
[单项选择]You are working on a software development project and there is 60% probability that development will be completed by the planned date and 70% probability that testing will be completed by the planned date.What is the probability that development and testing will be completed as per schedule ?()
A. 65%.
B. 42%.
C. 66%.
D. 63%.
[单项选择]In which phase of the software engineering process is the Software Requirements Specification developed ()
A. development phase
B. engineering phase
C. maintenance phase
D. Definition phase
[填空题]With the development of clever software, computing has been brought into ______.
[单项选择]Your project is in the planning phase and you are paid every fortnight for the work to be done during the fortnight. You have been informed by the project sponsor that there has been a revaluation of projects within your company and your project will not be getting any additional funding. In this case, you should ______.
A. stop work immediately and release all resources
B. perform appropriate closure for the project
C. decrease team size
D. remove non-critical tasks to decrease cost
[单项选择]The software development project is not going well.There are over 30 stakeholders,and no one can agree on the project objectives.One stakeholder believes the project can achieve a 30 percent improvement while another believes a 50 percent improvement is possible.The project manager thinks a 10 percent improvement is more realistic.What is the BEST course of action ?()
A. Move forward with the project and look for more information later to settle the issu
B. Average the numbers and use that as an objectiv
C. Perform a feasibility analysi
D. Ask the sponsor to make the final decisio
[单项选择]In schedule development, you create a distribution of probable results for each activity and use it to calculate distribution of probable results for the total project. The technique that you are using is ().
A. what-if analysis
B. mathematical analysis
C. Monte carlo analysis
D. resource leveling heuristic
[单项选择]The process of software development doesn't include()。
A. verification function
B. writing code
C. management function
D. validation function
[填空题]
{{B}}Tips for Saving Electricity{{/B}}
You probably don’t even realize it, but an energy thief is inside your
home at this very moment. This thief is silent and unseen, and he’s picking your
pocket. His name is "standby power". Standby power is the name given to the
electricity used to power electrical appliances and devices even when they are
turned off. But how can this be Isn’t an appliance "off" when you switch it
off Not necessarily.
Many electronic devices consume
electricity 24 hours a day just to stay warmed up for whenever you decide to use
them. "Instant on" TV sets are one example. Whether you watch TV seven hours a
day or not at all, the TV is always partially on, staying ready to flicker(闪烁)
to life the moment you turn on its switch.
Other devices that
consume power constantly are those that have external or internal clocks:
microwave ovens, computers, VCRs, DVD pla