题目详情
题目详情:
发布时间:2023-10-20 20:21:19

[单项选择]

A ()is a collection of projects and other work that are grouped together to facilitate effective management ofthat work to meet strategic business objectives.


A. program
B. portfolio
C. projectoflargesize
D. PMO

更多"A ()is a collection of projects and"的相关试题:

[单项选择]

In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()


A. Strongmatrix
B. Projectized
C. Projectcoordinator
D. Weakmatrix
[单项选择]

On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.


A. time estimating
B. cost estimating
C. project planning
D. schedule development
[名词解释]

英译中:Goods collection


[名词解释]英译中:Automatic Data Collection
[单项选择]

A project life cycle is a collection of generally sequential project()(1) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ()(2) for managing the project, regardless of the specific work involved.

空白(1)处应选择()
A. phases
B. processes
C. segments
D. pieces
[单项选择]Projects文件是文本文件(ASCII),其文件扩展名是()
A. apr
B. asp
C. arm
[单项选择]Documentary Collection is to be made with the documents to be()to the draft.
A. enclosed
B. attached
C. together
D. alongwith
[名词解释]

英译中:Automatic data collection(ADC)


[单项选择]

Project work packages are typically decomposed into smaller components called activities to provide a basis for()scheduling, executing, and monitoring and controllingthe proj ect work.


A. reviewing
B. estimating
C. auditing
D. expecting
[单项选择]

Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()


A. confused
B. same
C. overlap
D. dissever
[单项选择]

The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.


A. subdividing
B. assessing
C. planning
D. integrating
[单项选择]

()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.


A. Plannedvalue
B. Earned value
C. Actualcost
D. Costvariance
[单项选择]I tell my mother about my trials at work and brag() about the kids.
A. lie
B. boast
C. secretive
D. feelawkward
[单项选择]Without(), supply chain management doesn’t work.

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码