题目详情
当前位置:首页 > 职业培训考试
题目详情:
发布时间:2024-02-01 23:58:44

[单项选择]During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule ().
A. now becomes the new schedule, including the changes, and the original baseline is disregarded
B. is still the original baseline but annotated to reflect that a change has taken place
C. is amended to reflect the scope change, but the original baseline is still maintained for post-project review
D. is meaningless since every schedule update changes the baseline

更多"During project execution, the custo"的相关试题:

[单项选择]During execution of a project which is performed for a customer on a T & M (time and material)contract base, a new project manager is taking over the assignment. He discovers that two members assigned to the project have charged time without performing any work for the project customer. Upon further investigation, he determines that this occurred because there have been no other project assignments open for these employees. The customer is unaware of these facts. Which of the following should he do
A. Try to find some productive work for these staff members in the project and leave them on the team.
B. The best thing is to do nothing. The customer will not realize the problem anyway.
C. Try to find a responsible person for the over-assignment who can be made accountable.
D. Take the two people off the team immediately and arrange for the refund of the excess charges to the customer.
[单项选择]During half way to the project execution, you were assigned as a project manager. After careful reviewing of the project, you found that the project might take double the time that the previous manager estimated. However, the upper management has been told that the project is on schedule. The previous manager is an old friend of yours, what will you do ?()
A. Report your evaluation to the upper management
B. Have a team meeting to find the alternatives to meet the project schedule
C. Meet the previous project manager and turn the project back
D. Execute the project as planned by the previous manager
[单项选择]During the execution phase of the project, you realized the subcontractors are working with incomplete and different scope statements. As the project manager, what should you do FIRST ?()
A. Check the work completed against the correct scope statements
B. Review the scope of work with the stakeholders
C. Document the inconsistencies to management, calculating the cost of nonconformance
D. Stop all activities until the scope of the work complete
[单项选择]Reviewing schedules with the customer during the project planning phase shows the customer that ______.
A. you welcome their input
B. you want the customer to have visibility on actual project status
C. your company is good at marketing and customer relations
D. your competitors do it
[单项选择]At the beginning of project execution, you notice different opinions between team members relating to project work and deliverables and to the level of overall complexity. What should you do right now ?()
A. Give your team members some time to develop a common understanding of the project scope and product scope. Upcoming interface problems may be resolved later.
B. Use the risk management processes to identify and assess risks caused by misunderstandings and develop a plan with measures in order to respond to them.
C. Organize meetings to identify and resolve misunderstandings between team members in order to early avoid interface problems, disintegration and costly rework.
D. Use interviews in private with each individual team member to inform them of your expectations and your requirements in an atmosphere of confidence.
[单项选择]During execution, a functional manager asks you to use a model C generator of model B on your project. The functional manager says that model C will solve the needs of the project and provide some benefits to the manufacturing department. You look at the cost associated with model C and discover that it is substantially higher than model B. If you are not sure you can justify the more expensive model, what do you do
A. Review the specification of each to validate the manager’s claims.
B. Measure the differences in using each model and present them to senior management.
C. Use model C and cut other tasks to make up for the added cost.
D. Do a life cycle analysis and present the results to your boss.
[单项选择]While working on an external project your customer asks you to perform some additional tasks that are not included in the formal contract.You should ().
A. honor the customer's request as sign of cooperation to ensure future business
B. refuse the request and report the customer to your sponsor
C. acknowledge the request and advise the customer to submit a formal change request
D. convene a meeting of the project team and rewrite the scope statement
[单项选择]During a project the scope of a product purchased on a cost reimbursable contract has increased.In the contract the fee to cover the contractor's indirect costs and allow a profit is calculated as 20% of the direct costs.What is most likely to be true ?()
A. The contractor's indirect costs will increase and the customer's payment for them will increase,too
B. The contractor's indirect costs will increase but the eLlstomer's payment for them will not increase
C. Neither the contractor's indirect costs nor the customer's payment for them will increase
D. The contractor's indirect costs will not increase but the customer's payment for them will increase
[单项选择]You are running a project for a customer based on a cost reimbursable contract with the following terms: Target costs, $1000000; fix fee, 100000; benefit/cost sharing, 80/20; price ceiling, 1200000. Which is the PTA (point of total assumption, break point)of the project ?()
A. $1300000
B. $1500000
C. $80000
D. $1125000
[单项选择]During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised (75) are necessary.
[单项选择]During the project scope planning process, the work breakdown structure should be developed to ().
A. the sub-project level
B. the level determined by the project office
C. a level allowing for adequate estimates
D. the cost center level
[单项选择]A membership card authorizes ( ) the club's facilities for a period of 12 months.
A. the holder using
B. the holder's use
C. the holder to use
D. the holder uses
[填空题]customer service

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码